Country's first 12-lane scenic 300 feet road was to be inaugurated today

  • Staff Correspondent, Barta24.com
  • |
  • Font increase
  • Font Decrease

Photo: Collected

Photo: Collected

The country's widest and Southeast Asia's most scenic and attractive expressway is a 12-lane aesthetic 300 feet highway will be inaugurated today. This road is called the new gateway of modern Dhaka. The road has different levels of modern construction style and aesthetics.

It has 8 expressways. It will take only eight to 10 minutes to cross the road. In the meantime, 100% of the road work has been completed.

বিজ্ঞাপন

Prime Minister Sheikh Hasina will inaugurate the road virtually at 10 am on Tuesday (November 14).

Experts said that the road will create uninterrupted communication between Dhaka and neighboring districts besides Chattogram, Sylhet, Narsingdi and Gazipur which will be the guide of the country.

বিজ্ঞাপন

It is known that the road from Kuril flyover to Kanchan Bridge in Purbachal is only 12.5 km. This road will connect the Eastern Bypass with the city's Pragati Sarani and Airport Road.

According to the project sources, the 6 and a half kilometer road is being constructed with 12 lanes from Kuril of the capital to Balu river. Out of this 8 lane road will be an expressway. The remaining 4 lane roads will be service roads for local traffic.

Apart from this, the 6 km road from Balu River to Kanchan Bridge will have 12 lanes. Out of this 6 lane road will be an expressway. The remaining 4 lanes will be service roads.

At the same time, a total of 26 km of lakes have been excavated from Kuril to Balu river on both sides of Sheikh Hasina Sarani, 12.3 km, Boalia canal-5.2 km, Dumni canal-4.40 km for lake excavation and development.

The project includes excavation and development of the Nikunj Canal (750 m long). Apart from this, 13 arch bridges have been constructed on canals, 12 bridges have been constructed at different places on roads.

Five intersections have been created. Among them two intersections from Kuril to Balu river and three intersections from Balu river to Kanchan Bridge. Sluicegate and pump house have been constructed.

At the same time, 6 underpasses, 36.8 km walkway, 12.5 km boundary wall construction, foot over bridge at 6 places, 1170 road lights and 11 substations were installed and 60 thousand different species of trees were planted.

Incidentally, the first term of the project was from September 2015 to August 2018. The estimated cost of the project in 2015 was Tk. 5 thousand 286 crore 91 lakh. Due to the addition of three canals, roads, bridges, etc., the cost of the revised project has increased by about Tk. 5 thousand 42 crores 75 lakhs. The total cost of the project is Tk. 10 thousand 329 crore 66 lakh. Besides, the duration of the project has been extended till December 2023.